![IMG_3345](http://jlawrenceindustries.com/wp-content/uploads/2023/10/IMG_3345.jpg)
Recover project for a La Conner marine boat yard
JLI has an “Installation Team” experienced in Fabric Structure construction. The recover project is 60 feet wide by 120 feet long. The installation required 2 cranes to raise and drape the cover over the building. The JLI team completed the recover in 3 weeks.
![SDOT Fabric Structure installation SDOT Fabric Structure installation](http://jlawrenceindustries.com/wp-content/uploads/2023/10/IMG_4741.jpg)
SDOT Fabric Structure installation
JLI was responsible for Permits, Layout, Ecology Block Erection, Truss and cover Installation. The project took 2 weeks from start to finish. The building is 40′ x 50′. This will be used for Seattle Department of transportation, bulk material storage.
![IMG_7005](http://jlawrenceindustries.com/wp-content/uploads/2023/10/IMG_7005.jpeg)
Port of Everett Marina slip covers
Over head covers were installed to protect high value yachts and equipment from condensation and rust.